StacksVerified U.S. regulatory reference

40 CFR Part 63, Table 11

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
To comply withInspection or monitoring requirementFrequency of inspection or monitoringMethod
Tanks:
63.133(b)(1)Inspect fixed roof and all openings for leaksInitially Semi-annuallyVisual.
63.133(c)Inspect floating roof in accordance with §§ 63.120 (a)(2) and (a)(3)See § 63.120 (a)(2) and (a)(3)Visual.
63.133(d)Measure floating roof seal gaps in accordance with §§ 63.120 (b)(2)(i) through (b)(4)| See § 63.120 (b)(2)(i) through (b)(4).
—Primary seal gapsOnce every 5 years Initially Annually
—Secondary seal gaps
63.133(f) 63.133(g)Inspect wastewater tank for control equipment failures and improper work practicesInitially Semi-annuallyVisual.
Surface impoundments:
63.134(b)(1)Inspect cover and all openings for leaksInitially Semi-annuallyVisual.
63.134(c)Inspect surface impoundment for control equipment failures and improper work practicesInitially Semi-annuallyVisual.
Containers:
63.135(b)(1), 63.135(b)(2) (ii)Inspect cover and all openings for leaksInitially Semi-annuallyVisual.
63.135(d)(1)Inspect enclosure and all openings for leaksInitially Semi-annuallyVisual.
63.135(e)Inspect container for control equipment failures and improper work practicesInitially Semi-annuallyVisual.
Individual Drain Systems a:
63.136(b)(1)Inspect cover and all openings to ensure there are no gaps, cracks, or holesInitially Semi-annuallyVisual.
63.136(c)Inspect individual drain system for control equipment failures and improper work practicesInitially Semi-annuallyVisual.
63.136(e)(1)Verify that sufficient water is present to properly maintain integrity of water sealsInitially Semi-annuallyVisual.
63.136(e)(2), 63.136(f)(1)Inspect all drains using tightly-fitted caps or plugs to ensure caps and plugs are in place and properly installedInitially Semi-annuallyVisual.
63.136(f)(2)Inspect all junction boxes to ensure covers are in place and have no visible gaps, cracks, or holesInitially Semi-annuallyVisual or smoke test or other means as specified.
63.136(f)(3)Inspect unburied portion of all sewer lines for cracks and gapsInitially Semi-annuallyVisual.
Oil-water separators:
63.137(b)(1)Inspect fixed roof and all openings for leaksInitially Semi-annuallyVisual.
63.137(c)Measure floating roof seal gaps in accordance with 40 CFR 60.696(d)(1)Initially bSee 40 CFR 60.696(d)(1).
—Primary seal gapsOnce every 5 years
63.137(c)—Secondary seal gapsInitially b Annually
63.137(d)Inspect oil-water separator for control equipment failures and improper work practicesInitially Semi-annuallyVisual.

a As specified in § 63.136(a), the owner or operator shall comply with either the requirements of § 63.136 (b) and (c) or § 63.136 (e) and (f).

b Within 60 days of installation as specified in § 63.137(c).